Wind park development

With the receipt of 58,8MW permit from the Ministry of Economics of Latvia, our intention is to develop a wind farm of up to 17 turbines contributing to a sustainable energy future.

The project

AB Wind AS has acquired the permit and intends to build 58,8MW onshore wind farm.

Wind Power is still considered one of the cleanest energy sources with the highest conversion efficiency.

AB WIND will produce energy in area with the greatest potential for wind energy production implementing the regional sustainable development strategy.

Location Overview

Priekule parish, Southwest Latvia

• A territory located only 40 km from the sea shore
exclusively provides a favorable conditions for producing
energy from wind.

• Based on Dienvidkurzeme’s long term sustainable
development plan from July 28, 2022 (approved by local
municipality), use of area intended for wind farms.

Capacity

• Developer: AB Wind AS reg.Nr. 50203360371. Share capital 1.800.000 euro.

• Assets: 413ha purchased real estate land. Estimated market value around 2 million euro.

• Funding: Equity investment for around 4 million euro by now injected and distributed for the purchase of land, to cover the project’s initial development phase and ensure a security deposit to the public grid operator AST. 

Permits and technical documentation

Technical documentation
Permit of the Ministry of Economics No.: 3.11-8/2020/181 issued August 20, 2020 with a capacity of 58.8 MW for wind energy production. Signed Agreement with JSC "Augstsprieguma tīkli" on design and construction of power system substation, February, 2022.
Connection
Connection to the high voltage grid of JSC "Augstsprieguma tīkls" (AST) for 110kV power transmission line (PPA). Signed agreement on structured design of substation. Local Municipality’s permission for usage of municipality roads for underground grid networks to connect a 110kW sub-station with local wind power plant area.
Environmental requirements (IVN)
Environmental Impact Assessment (IVN). Signed contract with SIA “ELLE” on development of Environmental Impact Assessment (IVN). Deadline: Q2, 2024.
Ornithologist assessment
Preliminary positive initial assessment from the certified ornithologist. To be finalized by October 2023. Positive and final assesment on biotopes. July 2023.

Timeline

Permit of the Ministry of Economics
August, 2020
2020
Preliminary positive ornithologist assessment
March, 2021
2021
Signed contract for design task of the power substation
December, 2022
Signed agreement with public grid operator AST for design and construction of the power substation
February, 2022
2022
Ornithology assessments
October, 2023
Wind measurements by Lidar, in progress
July, 2023
Assesment on biotopes
July, 2023
2023
Power substation, infrastructure, road construction
June, 2024
Construction permit
May, 2024
Environment impact assessment
March, 2024
Technical design
February, 2024
2024
Power production starts
Q3, 2025
Installation, commissioning of wind turbines
Q2, 2025
2025